1.0.1 This Regulation is formulated with a view to strengthen the control over the establishment of the design documents on the construction project, and to ensure the quality and integrality of the design documents on different stages.
1.0.2 This Regulation is applicable to the construction, extension and renovation design of civil architecture, industrial factory building, warehouses and their auxiliary projects, both at home and abroad.
1.0.3 Not only the requirements stipulated in the national laws and regulations, but also those in the current relevant ones of the nation shall be complied with, of which, the compulsory engineering construction standards must be enforced strictly.
1.0.4 The civil architecture projects shall generally be divided into three stages: project design, preliminary design and construction documents design; for the civil architecture projects with relatively simple technical requirements, by the acceptance of the relevant competent department and without any preliminary design in the contract, it may direct enter the working drawing design stage after the examination and approval of project design.
1.0.5 The preparation depth of design documents in various stages shall be made according to the following principles (the specific provisions shall comply with articles of Chapter 2, 3 and 4):
1 Project design documents shall meet the requirements for the preparation of the preliminary design documents.
Note: This Regulation is only applicable to the depth of document preparation for approval project design, while the depth of the preparation of bid proposal design documents shall comply with relevant provisions issued by the Ministry of Housing and Urban-Rural Construction.
2 Preliminary design documents shall meet the requirements for the preparation of the construction documents design.
3 The construction documents design shall meet the requirements of equipment and material procurement, non-standard equipment fabrication and construction. For the conditions of sub-contracting projects respectively to several design organizations or implementing the design subcontract, the depth of the interlocked section of the design documents shall meet the design requirements of the contractor or subcontractor.
1.0.6 The design should be treated in accordance with local conditions, so as to correctly select the national, professional and local building standards design, and indicate clearly the title of the application atlas shown in the drawing list or construction documents design explanation of the design documents.
When repeatedly using other engineering drawings, the dedicated person shall learn more about the conditions and content used by the original drawing, and make necessary accounting and modification, so as to meet the requirements of the new design project.
1.0.7 When the design contract has special requirements for the preparation depth of the design documents, the required preparation depth of the design documents shall also meet requirements of this Regulation and the design contract.
1.0.8 This Regulation is generally used for the preparation depth of the design documents. However, for the specific engineering project design, provisions of this Regulation shall be rationally selected according to the project content and scope of design.
1.0.9 This Regulation cannot be used as the basis for the professional design division. Some professional design content of this Regulation may be designed by some other professions, but the depth of the design documents shall meet the requirements of this Regulation.
Contents 1. General Provisions 2. Project Design 2.1 General Requirements 2.2 Design Specifications 2.3 Design Drawing 3. Preliminary Design 3.1 General Requirements 3.2 General Design Specification 3.3 General Plane 3.4 Building 3.5 Structure 3.6 Building Electricity 3.7 Water Supply and Drainage 3.8 Heating, Ventilation and Air Conditioning (HVAC) 3.9 Thermal Power 3.10 Preliminary Estimate 4. Design of Construction Drawing 4.1 General Requirements 4.2 General Plan 4.3 Building 4.4 Structure 4.5 Building Electrical 4.6 Water Supply and Drainage 4.7 Heating / Ventilation and Air Conditioning (HVAC) 4.8 Thermal Power Engineering 4.9 Budget
Standard
Jian Zhi [2008] No.216 Provisions on Depth for Preparation of Design Document for Construction Work (2008 Edition) (English Version)
Standard No.
Jian Zhi [2008] No.216
Status
superseded
Language
English
File Format
PDF
Word Count
30000 words
Price(USD)
600.0
Implemented on
2008-11-26
Delivery
via email in 1 business day
Detail of Jian Zhi [2008] No.216
Standard No.
Jian Zhi [2008] No.216
English Name
Provisions on Depth for Preparation of Design Document for Construction Work (2008 Edition)
1. General Provisions
1.0.1 This Regulation is formulated with a view to strengthen the control over the establishment of the design documents on the construction project, and to ensure the quality and integrality of the design documents on different stages.
1.0.2 This Regulation is applicable to the construction, extension and renovation design of civil architecture, industrial factory building, warehouses and their auxiliary projects, both at home and abroad.
1.0.3 Not only the requirements stipulated in the national laws and regulations, but also those in the current relevant ones of the nation shall be complied with, of which, the compulsory engineering construction standards must be enforced strictly.
1.0.4 The civil architecture projects shall generally be divided into three stages: project design, preliminary design and construction documents design; for the civil architecture projects with relatively simple technical requirements, by the acceptance of the relevant competent department and without any preliminary design in the contract, it may direct enter the working drawing design stage after the examination and approval of project design.
1.0.5 The preparation depth of design documents in various stages shall be made according to the following principles (the specific provisions shall comply with articles of Chapter 2, 3 and 4):
1 Project design documents shall meet the requirements for the preparation of the preliminary design documents.
Note: This Regulation is only applicable to the depth of document preparation for approval project design, while the depth of the preparation of bid proposal design documents shall comply with relevant provisions issued by the Ministry of Housing and Urban-Rural Construction.
2 Preliminary design documents shall meet the requirements for the preparation of the construction documents design.
3 The construction documents design shall meet the requirements of equipment and material procurement, non-standard equipment fabrication and construction. For the conditions of sub-contracting projects respectively to several design organizations or implementing the design subcontract, the depth of the interlocked section of the design documents shall meet the design requirements of the contractor or subcontractor.
1.0.6 The design should be treated in accordance with local conditions, so as to correctly select the national, professional and local building standards design, and indicate clearly the title of the application atlas shown in the drawing list or construction documents design explanation of the design documents.
When repeatedly using other engineering drawings, the dedicated person shall learn more about the conditions and content used by the original drawing, and make necessary accounting and modification, so as to meet the requirements of the new design project.
1.0.7 When the design contract has special requirements for the preparation depth of the design documents, the required preparation depth of the design documents shall also meet requirements of this Regulation and the design contract.
1.0.8 This Regulation is generally used for the preparation depth of the design documents. However, for the specific engineering project design, provisions of this Regulation shall be rationally selected according to the project content and scope of design.
1.0.9 This Regulation cannot be used as the basis for the professional design division. Some professional design content of this Regulation may be designed by some other professions, but the depth of the design documents shall meet the requirements of this Regulation.
Contents of Jian Zhi [2008] No.216
Contents
1. General Provisions
2. Project Design
2.1 General Requirements
2.2 Design Specifications
2.3 Design Drawing
3. Preliminary Design
3.1 General Requirements
3.2 General Design Specification
3.3 General Plane
3.4 Building
3.5 Structure
3.6 Building Electricity
3.7 Water Supply and Drainage
3.8 Heating, Ventilation and Air Conditioning (HVAC)
3.9 Thermal Power
3.10 Preliminary Estimate
4. Design of Construction Drawing
4.1 General Requirements
4.2 General Plan
4.3 Building
4.4 Structure
4.5 Building Electrical
4.6 Water Supply and Drainage
4.7 Heating / Ventilation and Air Conditioning (HVAC)
4.8 Thermal Power Engineering
4.9 Budget